The Old Airfield Solar Farm (Solar , Active) Location in the UK : England, NR9 5JF Type of installation: Solar on/offshore: on Solar Panels :0 Capacity : 10 MW Approx Date of 1st power generation: March 2015
/YES
DEBUG comment: caniedit 1 = public DEBUG comment: caniedit 2 = public DEBUG comment SQL: select * from [energymaplocs].[dbo].vmycomment where main_id=3558 and typeofcomment <> 'delete' and ( added_by = 0 or typeofcomment = 'public' ) Weston Longville Solar The Old Airfield, Airfield Lane, Weston Longville, Norwich, Norfolk, NR9 5JF
Relationship |
Company (For:
The Old Airfield
) |
DBUG:SQL Command = select top 40 * from energymaplocs.dbo.vco_proj_type where cp_project = 3558 order by c_compname asc
Developer | Lumicity Ltd |
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
got here Got here pop 2 projectid = 3558 vdeccref = DEBUG decclib sql = select *, [Installed Capacity (Elec)] as installed_capacity, [Contractor (/Applicant)] as contractor from energymaplocs.dbo.vdeccofgem_project where dop_deccorofgem = 'DECC' and dop_project = '3558' order by [planning application submitted] desc
Site Name: |
The Old Airfield 5 MW
|
Energy Type: |
Solar Photovoltaics |
County: |
Norfolk Country: England LPA: Broadland District Council
|
Site ID and Reference: |
2072 / C2224
District:
|
Applicant: |
Lumicity
Application :
20131702
|
(Go to search to find Application) |
|
--- For Solar Farms / Parks --- |
Mounting of panels: |
Ground |
|
|
|
--- ----- ---- --- |
Site Address: |
The Old Airfield, Airfield Lane, Weston Longville, Norwich
|
|
NR9 5JF
|
County: |
Norfolk Region: Eastern
|
OS Coordinates: |
609858 / 609858
|
Development Status: |
Operational
|
Application Submitted: |
12/3/2013
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
|
Construction Date: |
1/1/2015
|
|
|
Generator Live |
3/31/2015
|
This Record Last Updated: |
5/29/2015
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
|
DEBUG Ofgemlib sql = select * from energymaplocs.dbo.vdeccofgem_project where dop_deccorofgem = 'OFGEM' and dop_project = '3558' order by CommissionDate desc
Site Name: |
Weston Longville Solar
|
Generator Type: |
Photovoltaic (RO code = RU)
|
Scheme : |
RO
|
Generator ID: |
R00436RUEN
|
Capacity: |
5500
|
Status: |
Live
|
Accreditation Date: |
12/3/2013
|
|
|
Commission Date: |
3/31/2015
|
|
|
Applicant: |
Perpetual Power (UK) Limited
|
Applicant Address: |
C/O Quintas Energy UK Ltd
Suite C, 3rd Floor,
3 Harbour Exchange Square,
London
E14 9GE
England
|
Address: |
Weston Longville G1 Solar Farm Limited
The Old Airfield
Weston Longville
NR9 5JF
England
|
Site Name: |
Weston Longville Solar
|
Generator Type: |
Photovoltaic
|
Scheme : |
REGO
|
Generator ID: |
G06010PVEN
|
Capacity: |
5500
|
Status: |
Live
|
Accreditation Date: |
12/3/2013
|
|
|
Commission Date: |
3/31/2015
|
|
|
Applicant: |
Perpetual Power (UK) Limited
|
Applicant Address: |
C/O Quintas Energy UK Ltd
Suite C, 3rd Floor,
3 Harbour Exchange Square,
London
E14 9GE
England
|
Address: |
Weston Longville G1 Solar Farm Limited
The Old Airfield
Weston Longville
NR9 5JF
England
|
|
Assumptions: Capacity: 5500kW 5.5 MW, Thus over the month Capacity * 720 hours per month = 3960 MWh
|
Output Period |
LECs Issued |
ROCs Issued |
REGO Certs |
Capacity Factor |
Status |
DBUG:SQL Command = select * from energymaplocs.dbo.rego where [Accreditation Number] = 'G06010PVEN' order by output_year desc, output_month desc
01/03/2018 | | | 469 | 8.53% | Issued | 01/02/2018 | | | 352 | 6.40% | Issued | 01/01/2018 | | | 180 | 3.27% | Issued | 01/12/2017 | | | 146 | 2.65% | Issued | 01/11/2017 | | | 261 | 4.75% | Issued | 01/10/2017 | | | 376 | 6.84% | Issued | 01/09/2017 | | | 647 | 11.76% | Issued | 01/08/2017 | | | 864 | 15.71% | Issued | 01/07/2017 | | | 928 | 16.87% | Issued | 01/06/2017 | | | 952 | 17.31% | Issued | 01/05/2017 | | | 960 | 17.45% | Issued | 01/04/2017 | | | 869 | 15.80% | Issued | 01/03/2017 | | | 691 | 12.56% | Redeemed | 01/02/2017 | | | 273 | 4.96% | Redeemed | 01/01/2017 | | | 210 | 3.82% | Redeemed | Dec-16 | 0 | 208 | 156 | 2.84% | Issued | Nov-16 | 0 | 349 | 256 | 4.65% | Issued | Oct-16 | 0 | 621 | 448 | 8.15% | Issued | Sep-16 | 0 | 886 | 637 | 11.58% | Issued | Aug-16 | 0 | 1284 | 917 | 16.67% | Issued | Jul-16 | 0 | 1310 | 936 | 17.02% | Issued | Jun-16 | 0 | 1078 | 770 | 14.00% | Issued | Jun-16 | 0 | 1078 | 770 | 14.00% | Issued | May-16 | 0 | 1317 | 941 | 17.11% | Issued | Apr-16 | 0 | 1166 | 833 | 15.15% | Issued | Mar-16 | 0 | 824 | 594 | 10.80% | Redeemed | Feb-16 | 0 | 567 | 411 | 7.47% | Redeemed | Jan-16 | 0 | 279 | 207 | 3.76% | Redeemed | Dec-15 | 0 | 180 | 136 | 2.47% | Redeemed | Nov-15 | 0 | 240 | 178 | 3.24% | Redeemed | Oct-15 | 0 | 567 | 411 | 7.47% | Redeemed | Sep-15 | 0 | 908 | 653 | 11.87% | Redeemed | Aug-15 | 0 | 895 | 639 | 11.62% | Redeemed | Jul-15 | 890 | 1246 | 890 | 16.18% | Redeemed | Jun-15 | 992 | 1389 | 992 | 18.04% | Redeemed | May-15 | 975 | 1365 | 975 | 17.73% | Redeemed | Apr-15 | 831 | 1164 | 831 | 15.11% | Redeemed | Mar-15 | 27 | 38 | 28 | 0.51% | Redeemed |
|
Project Info |
DBUG:SQL Command = 'select top 5 * from [energymaplocs].[dbo].hr_doc_indexes where title+summary like '%The Old Airfield%' and type_id=2 or (type_id=6 and project_id = 3558 ) order by dated desc' ViewEdit = 1 DocTypeID = 9 SubjectTypeID = -1 -- select top 5 * from [energymaplocs].[dbo].hr_doc_indexes where title+summary like '%The Old Airfield%' and type_id=2 or (type_id=6 and project_id = 3558 ) order by dated descSorry I found no matches, Please try again.
|
|
©2018
Simon Mallett |
Latest News Added |
DBUG:SQL Command = 'select top 5 * from [energymaplocs].[dbo].hr_doc_indexes where title+summary like '%%' and type_id=2 order by dated desc' ViewEdit = 1 DocTypeID = 2 SubjectTypeID = -1 -- select top 5 * from [energymaplocs].[dbo].hr_doc_indexes where title+summary like '%%' and type_id=2 order by dated descLarport Solar Farm The land identified for the solar project is to the south of the Clay Hill Pit Substation at Dormington and has been chosen for its potential to deliver solar powered electricity. Date and Time of entry: Thursday, January 2, 2025 00:00
Larport Solar Farm Larport Solar Farm is a 45MW project in Herefordshire, UK. It was the first solar PV project developed by Conrad Energy. Ethical Power was selected as the principal contractor Date and Time of entry: Thursday, January 2, 2025 00:00
Bracks Solar Farm Bracks Farm Solar Park Limited is building a 30MWp solar farm in Cambridgeshire. It has the capacity to produce enough electricity to power approximately 8,000 households per year*. Date and Time of entry: Thursday, January 2, 2025 00:00
Northfield House Farm Solar PV Park, UK Northfield House Farm Solar PV Park is a 26MW solar PV power project. Date and Time of entry: Thursday, January 2, 2025 00:00
Streetfields and Northfield House solar 54,400MWh
renewable energy generated per year Date and Time of entry: Thursday, January 2, 2025 00:00
|
|