Page views this IP this session = 3 of 10 unsubscribed pagesBrenig Wind Farm
Click here for Generation Forecast for wind farms based on Met office data
Brenig Wind Farm (Wind , Active) Location in the UK : Wales, Denbigh, North Wales Type of installation: Wind on/offshore: on Turbines :16 Capacity : 40 MW Approx Date of 1st power generation: October 2018
Wind Turbines, Wind Farm, Renewable Energy, Green Power
/YES
Although initial scoping of the site showed that the proposed site at Brenig might be suitable for up to 23 turbines, after applying a number of project constraints on the area and taking into account the views of local people, the number of wind turbines was reduced to 16 in the 2-2.5MW range.
The consented development of 16 turbines will have the installed generation capacity of up to 40MW of electricity, enough to power the annual equivalent demand of 20,000+ homes. On average it is envisaged that the wind farm will produce an output of 105,120MW hours/year, i.e. 30% of what it would produce if it were operating continually at maximum output.
During the 25 year lifetime it will cut emissions of carbon dioxide by 2.26million tonnes, sulphur dioxide by 2,625 tonnes, and nitrous oxide by 525 tonnes, helping to combat climate change.
Model: |
Vestas V80
|
Start Speed: |
4
|
Capacity: |
2
|
Optimal Speed: |
15
|
Rotor Diameter: |
80
|
Stop Speed: |
25
|
Hub Height |
60 Avg for all turbines:60
|
Avg. Elevation: |
469
|
Web Page: |
|
Comment: |
|
Relationship |
Company (For:
Brenig
) |
Sorry I found no matches, Please try again.
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
Brenig Wind Farm 37.6 MW
|
Energy Type: |
Wind Onshore |
County: |
Denbighshire Country: Wales LPA: Denbighshire County Council
|
Site ID and Reference: |
5598 /
District:
|
Applicant: |
CGNEE
Application :
25/2015/0636
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
16 |
Turbine Capacity: |
2.3500000000000001 |
Height of Turbines: |
110 |
Calculated capacity: |
37.6 |
Site Address: |
Land east of Llyn Brenig, Nantglyn, Denbigh,
|
|
|
County: |
Denbighshire Region: Wales
|
OS Coordinates: |
299481 / 299481
|
Development Status: |
Operational
|
Application Submitted: |
6/18/2015
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
11/19/2015
|
Construction Date: |
8/24/2017
|
|
|
Generator Live |
10/15/2018
|
This Record Last Updated: |
11/21/2018
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
1/27/2016 |
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
11/19/2015 |
Site Name: |
Brenig Wind Farm 40 MW
|
Energy Type: |
Wind Onshore |
County: |
Denbighshire Country: Wales LPA: Denbighshire County Council
|
Site ID and Reference: |
4082 / A0160
District:
|
Applicant: |
Wind Power Wales
Application :
25/2007/0565
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
16 |
Turbine Capacity: |
2.5 |
Height of Turbines: |
|
Calculated capacity: |
40 |
Site Address: |
Denbigh Moors, Denbigh,
|
|
|
County: |
Denbighshire Region: Wales
|
OS Coordinates: |
304304 / 304304
|
Development Status: |
Revised
|
Application Submitted: |
4/26/2007
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
|
Construction Date: |
|
|
|
Generator Live |
|
This Record Last Updated: |
5/31/2016
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
|
Capacity: 80 Start Speed: 5 m/s (11.185 mph) Optimum Speed: 15 m/s (33.555 mph) Stop Speed: 25 m/s (55.925 mph)
Local Weather Station: Elevation of Weather Station:
Date for Wind forecast: 5/3/2025 Wind Speed at Weather Station: mph Wind Direction: Outputratio = 0.00 Output of Wind Farm = 0.0
Project Info |
|
©2018
Simon Mallett |
Latest News Added |
Larport Solar Farm The land identified for the solar project is to the south of the Clay Hill Pit Substation at Dormington and has been chosen for its potential to deliver solar powered electricity. Date and Time of entry: Thursday, January 2, 2025 00:00
Larport Solar Farm Larport Solar Farm is a 45MW project in Herefordshire, UK. It was the first solar PV project developed by Conrad Energy. Ethical Power was selected as the principal contractor Date and Time of entry: Thursday, January 2, 2025 00:00
Bracks Solar Farm Bracks Farm Solar Park Limited is building a 30MWp solar farm in Cambridgeshire. It has the capacity to produce enough electricity to power approximately 8,000 households per year*. Date and Time of entry: Thursday, January 2, 2025 00:00
Northfield House Farm Solar PV Park, UK Northfield House Farm Solar PV Park is a 26MW solar PV power project. Date and Time of entry: Thursday, January 2, 2025 00:00
Streetfields and Northfield House solar 54,400MWh
renewable energy generated per year Date and Time of entry: Thursday, January 2, 2025 00:00
|
|
©2017
Simon Mallett |
|